Mettur Annamalai Power Station: 210 MW production stopped as 4th unit undergoes 50‑day maintenance

Source: Dinamani ↗

210 megawatts of power generation has been stopped at Mettur Annamalai Power Station.

The stoppage is due to maintenance work on the fourth unit of the first stage. Production has been halted since Saturday morning.

Mettur Annamalai Power Station operates two stages. The first stage has four units each with a capacity of 210 megawatts, producing a total of 840 megawatts.

The second stage has one unit with a capacity of 600 megawatts, producing 600 megawatts. In total, 1,440 megawatts of power had been generated.

Maintenance of 50 days is scheduled for the fourth unit of the first stage. Engineers of the power station said that after the work is completed, steps will be taken to restart power generation.

Full details

Place
Mettur
மேட்டூர் அனல் மின் நிலையத்தின் 4-ஆவது அலகில் பராமரிப்புப் பணி நடைபெறுவதால் 210 மெகாவாட் மின் உற்பத்தி நிறுத்தப்பட்டுள்ளது.
மேட்டூர் அனல் மின் நிலையத்தில் இரண்டு பிரிவுகள் செயல்பட்டு வருகின்றன.
முதல் பிரிவில் தலா 210 மெகாவாட் திறன் கொண்ட 4 அலகுகள் மூலம் 840 மெகாவாட் மின்சாரம் உற்பத்தி செய்யப்பட்டது.
இரண்டாவது பிரிவில் 600 மெகாவாட் திறன் கொண்ட ஓர் அலகு மூலம் 600 மெகாவாட் மின்சாரம் உற்பத்தி செய்யப்பட்டது.
மொத்தம் 1440 மெகாவாட் மின்சாரம் உற்பத்தி செய்யப்பட்டு வந்தது.
முதல் பிரிவின் 4-ஆவது அலகில் 50 நாள்கள் பராமரிப்புப் பணிகள் திட்டமிடப்பட்டுள்ளதை அடுத்து, சனிக்கிழமை காலை முதல் 210 மெகாவாட் உற்பத்தி நிறுத்தப்பட்டுள்ளது.
பராமரிப்புப் பணிகள் நிறைவடைந்த பின்னர் மீண்டும் மின் உற்பத்தியைத் தொடங்குவதற்கான நடவடிக்கைகள் மேற்கொள்ளப்படும் என அனல் மின் நிலைய பொறியாளர்கள் தெரிவித்தனர்.